Conductor Pile Driving Operation
PROJECT: | BATCH WELL OPERATION
26’’ x 0.75’’ CONDUCTOR PILING (7 SLOT) 30’’ x 1’’ CONDUCTOR PILING (1 SLOT) |
FACILITY: | BALTIC & FRIGGS |
WELL: | OFD 3 |
DURATION: | 14 DAYS |
DATE: | 20/12/2018 – 5/01/2019 |
PROJECT OPERATION OVERVIEW
The 26’’ Conductor Pile driving was carried out on a Jack-up Rig for our client, the operation involved 7 slot batch piling of 26″ Conductor pile on Rig BALTIC and 1 slot piling of 30″ Conductor Pile on Rig FRIGGS using an IHC Hydraulic Hammer until desired depth,the operation was a success.
Why Should You Use Us
Bamor projects are carried out as professionally as possible, meeting all specified quality requirements, with the aim of ensuring customer satisfaction & zero complaint at the end of every project delivered.
- Expertise: We mobilized competent personnel and equipment for all field engineering operations.
- Efficiency: we deliver services to our customers in a timely, cost effective and safe manner.
- Competitive prices: Our services guarantee no hidden fee. We are able to offer prices that are transparent.